In June 2019 the construction of the connection local heating line in Enkenbach-Alsenborn will start.

This 1 000 m long pipe across Enkenbach-Alsenborn will connect the existing wood chip heating plant with the biomass heating plant system, resulting in a better supply security. The connection line contains a feed and a return line, each with an inner diameter of 200 mm. Due to the big length of the pipe and the multitude of traffic-related dependency the connection will be built in three phases. The first and the second section will start in summer 2019 and the realization of the third section is planned in summer 2020.

igr took over the whole route planning and is responsible for construction supervision.