Planning the cable route for the Worms 2 wind park, Worms
Our client wanted to create the Worms 2 wind park with a nominal output of ca. 3 MWp. The wind park, consisting of seven wind energy plants, was sited in the Pfeddersheim, Abenheim and Mörstadt districts. igr was commissioned with the planning and the securing of easements for the cable route from the wind park to the feed-in point.
In cooperation with the environmental authorities, the ecological inspections of the entire route were carried out, and the water law authorisations for every waterway crossing applied for. To list and investigate every service line crossing point, all the relevant service providers were contacted. The implementation plan concluded with survey point lists and tender documents. Besides technical civil engineering planning, the project included on-site construction supervision, construction surveying, as-built surveying and processing documentation.
Services provided by igr
- Planning of engineering constructions
- Planning of technical equipment
- Route finding with three options
- Authorisation applications concerning railways, waterways, motorways, state and district roads and gas lines
- Securing of easements for the entire route
- Implementation planning with survey point lists for the cable route
- On-site construction supervision
- Construction surveying and as-built surveying
- As-built documentation and plans
Key figures
- Securing of easements to cross ca. 25 private properties
- 9 horizontal directional drilling bores at crossing points
- Cable length/specification:
- ca. 3,9 km/3x1x150 mm² NAXS(F)2Y
- ca. 10,3 km/3x1x400 mm² NAXS(F)2Y
- ca. 7,9 km/3x1x500 mm² NAXS(F)2Y